Chapter V Chapter 1 Preparation of the purpose of the mining schedule

The mining schedule, also known as the production schedule, is a guiding plan for the mine to schedule annual production after the infrastructure schedule.

The mining schedule is based on conditions such as a reasonable advance relationship in the mining sequence, the production capacity of the ore block, and the preparation time of the new level. Generally, it should be compiled from the year when the mine is put into production to reach the design capacity, and the annual mining plan and the mining grade after the production is completed, and the workload and schedule will be digged year by year.

As a general rule, the mining schedule is compiled by the design department and reaches the mine along with the preliminary design. The mining production department then plans the annual and quarterly mining operations according to the mining schedule to guide production.

Chapter 1 Requirements for the preparation of the mining schedule

Section 1 Purpose of the plan

(1) In order to verify the year-on-year development of mining recovery and mining work;

(2) On the basis of production verification, further verify whether the mine can reach the designed production capacity within the predetermined time limit according to the mining technical conditions, and whether it can continue to stabilize production after reaching the designed production capacity;

(3) The order in which the ore bodies, stages and ore blocks are harvested, the annual ore production and quality, and the date on which the mine is put into production and the juice production is reached;

(4) Determine the level of advancement required for the mining of the cutting work;

(5) Determine the number of personnel and equipment required for mining work.

Section 2 Requirements for the preparation of the plan

The mining schedule is essentially the specificization of all mining design technology decisions, and is the main basis for other professional design. Therefore , in the preparation of the mine must be combined with the characteristics of each mine , to make detailed and detailed arrangements; plan to reflect the party's mining technology policy; the various technical production quotas used in the plan, to be practical and feasible; completed during the planning period The amount of work should be as balanced as possible; and the plan must be both average and advanced.

Charts and captions should be clear and accurate.

GYSB0530B sieving Mixing Machine is a kind of Road Maintenance Machine primarily used to screen and mix aggregates for Chip Seal . It can also be used to wash aggregates if equipped with optional accessories.

Technical Specifications of Sieving Mixing Machine
Aggregates Graininess ≤30mm
Productivity 15~35t/h
Voltage 380V
Frequency 50 Hz
Gross Power 13 kWh
Weight 6t
Overall Dimensions 5600×1800×2800 (mm)

Our company is an ISO9001 certified sieving mixing machine manufacturer, located in China. In order to keep up with customers' needs, we offer a wide range of road maintenance equipment, such as Road Sweeper Machine, shot blaster, snow plough, and more. As our products are reliable, economical and durable, they are very popular with customers from Poland, Russia, Indonesia, Vietnam, Kazakhstan, Kyrgyzstan, among other countries. 
For more information, please feel secure in contacting us.

Screening Mixing Machine

Screening Mixing Machine

Screening Mixing Machine ,Mixing Machine,Powder Mixer Machine,Cement Mixer Machine

Henan Gaoyuan Road Maintenance Equipment Co., Ltd. , https://www.sgroadmachinary.com

Posted on